PJM Reliability Resource Initiative (RRI) Site Control: What the 51 Selected Projects Need to Know in TC2
PJM selected 51 RRI projects on May 2, 2025, totaling 9,361 MW UCAP. Those projects are now in Transition Cycle #2 with Decision Point I approaching. The site control submitted at the March 14, 2025 RRI Application Deadline carried a one-year minimum term — which has now expired. Here is what the 51 need to do next.
The 51 in plain numbers
On May 2, 2025, PJM selected 51 projects from a pool of 94 RRI applications. The cap was originally 50 projects; a tie in the weighted scoring pushed the count to 51. Together, the selected portfolio represents 9,361 MW of unforced capacity (UCAP) — 2,108 MW from 39 uprates and 7,253 MW from 12 new-build projects.
The technology mix is heavier on thermal and nuclear than the typical PJM queue. Of the 12 new-build projects, six are gas combined cycle, five are battery storage, and one is nuclear. The 39 uprates apply to existing natural gas, nuclear, coal, and onshore wind assets. Roughly 90% of the portfolio is targeted for commercial operation by 2030, with the remainder by 2031.
RRI was created under FERC Docket No. ER25-712-000, filed December 14, 2024, and accepted by FERC on February 11, 2025. The implementing rules sit in Tariff Part VII, Subpart C, Sections 305 and 306, with site control governed by the standard Tariff Part VII, Subpart A, Section 302 and Manual 14H Section 7.
Why this guide is for the next 60 days
The site control evidence each RRI applicant submitted on or before March 14, 2025 had to demonstrate exclusivity for a minimum term of one year from the Application Deadline. That minimum term expired on or around March 14, 2026 — about six weeks ago. RRI projects in TC2 are now operating either on extended/refreshed instruments or on instruments that have lapsed below the Section 302 standard.
Decision Point I is the first place that gap becomes visible to PJM. At DP1, RRI projects must submit a refreshed Site Control Review Spreadsheet, with the Document Details and Decision Point 1 tabs both completed. Site control evidence is compared against the initial Site established at application. Anything missing, expired, or non-conforming converts into a deficiency under the Application Review Phase procedure in Tariff Part VII, Subpart C, Section 306(B) — the same 10-business-day cure clock that governs Cycle 1 applicants.
How RRI site control evidence works
RRI applicants submitted site control under the standard PJM evidentiary framework. There is no separate RRI-only evidence pathway. The accepted instruments at application were:
- Deed — for owned property
- Lease — fully executed, not a memorandum
- Option to lease or option to purchase — with a minimum one-year term from the Application Deadline
- Site control in any form the entity issues — for sites controlled by a government entity
Three categories of evidence were explicitly disqualified, and remain disqualified going into DP1:
- A memorandum of any underlying instrument
- Evidence of intent to purchase
- Site control on a parcel that is the subject of an interconnection request in an adjacent RTO/ISO
Evidence had to demonstrate exclusivity, term (minimum one year from the Application Deadline), and conveyance. This is the same triad applied to all PJM new service requests under Section 302.
RRI density rules and the PE-stamped layout
Manual 14H Section 7.1.6 sets minimum acreage per technology, applied identically to RRI applicants and Cycle 1 applicants. The figures below were the controlling standard at the March 14, 2025 RRI Application Deadline and remain the standard at TC2 DP1.
| Technology | Required Acreage |
|---|---|
| Solar | 5 acres/MW |
| Wind | 30 acres/MW |
| Battery Storage | 1 acre per 100 MWh |
| Synchronous Generator (gas, nuclear, coal, etc.) | 10 acres per facility |
Where actual project density exceeded what Manual 14H allows, the applicant had to provide a Site Plan stamped by a Professional Engineer licensed in the state of the facility location. The PE-stamped drawing must specify the proposed generation arrangement and the Maximum Facility Output. The same rule controls at DP1: any density change between application and DP1 requires a refreshed PE-stamped layout.
The RRI Officer Certification — same form, sharper consequences
Every RRI application required a Site Control Officer Certification executed by an officer of the Project Developer entity, not the parent. The certification serves as the Section 302 attestation and as the verification of the Critical Path Construction Schedule. PJM's published instruction is unambiguous: any application without the attestation is considered incomplete.
For RRI projects, the consequences of a defective Officer Certification are sharper than in Cycle 1 because of the upstream commitments built into Sections 305 and 306. An RRI Project that obtains a GIA or WMPA must be offered into the Reliability Pricing Model auction or committed to a Fixed Resource Requirement plan for ten consecutive delivery years. The categorical capacity must-offer exemptions in Tariff Attachment DD, Section 6.6A do not apply. A flawed certification at DP1 that triggers withdrawal forfeits the RRI Deposit and unwinds those downstream commitments.
Parcel modifications between Application, DP1, and DP3
The Site submitted at the RRI Application Deadline established the initial Site — the spatial baseline against which DP1 and DP3 submissions are compared. Manual 14H Section 7.2 defines a precise modification grammar at each Decision Point, updated in PJM's July 23, 2025 Manual 14H update (FERC Docket EL25-22-000 and ER25-1544-000, accepted June 10, 2025).
| Stage | Site Control Demonstration | Allowed Modifications |
|---|---|---|
| Application Phase | Required — establishes initial Site | n/a |
| Decision Point I | Required — compared to Application | Add adjacent parcels OR parcels with recorded easement to initial Site; remove any parcels without demonstration |
| Decision Point II | Not required | Changes evaluated against DP3 modification rules |
| Decision Point III | Required — compared to DP1 | Same as DP1; modifications to interconnection facilities or switchyard parcels do not affect issued System Impact Studies |
| Post-WMPA/GIA | Required — per Schedule A | Attestation that change does not impact milestones, OR Necessary Studies Agreement required |
The two operational rules to internalize for RRI projects approaching DP1 are: (1) any parcel addition must be adjacent or have recorded easement evidence back to the initial Site, and (2) the Generating Facility, including the high side of the Main Power Transformer, must continue to be covered at 100% under the density rules.
Cycle 1 vs RRI vs Transition Cycle #2: site control compared
The single most useful comparison for an RRI applicant evaluating where they sit relative to peers in the PJM queue is across the three concurrent application paths. The site control evidentiary standard is identical across all three. The financial and commercial consequences of a deficiency are not.
| Dimension | Cycle 1 | RRI | TC2 (legacy) |
|---|---|---|---|
| Application Deadline | April 27, 2026 | March 14, 2025 | December 17, 2024 |
| Site Control standard | Section 302 / M-14H §7 | Section 302 / M-14H §7 | Section 302 / M-14H §7 |
| Coverage at application | 100% Generating Facility + MPT high side | 100% Generating Facility + MPT high side | Per legacy queue rules at original submission |
| Term minimum | 1 year from Application Deadline | 1 year from March 14, 2025 | Per original submission |
| Officer Certification | Cycle 1 template | RRI template | Pre-existing attestation |
| Deposit at risk | Study + Readiness | Study + Readiness + RRI Deposit | Existing deposits |
| Capacity must-offer commitment | Standard | RPM/FRR for 10 consecutive delivery years | Standard |
| One-year milestone extension | Available under §6.5 of GIA | Waived — not available | Available under §6.5 of GIA |
The deposit math behind the urgency
Each selected RRI project posted three deposits at the March 14, 2025 Application Deadline. Two are standard for any TC2 applicant; the third is RRI-specific.
- Study Deposit — tiered by project size from $75,000 (0–20 MW) to $400,000 (>750 MW). Ten percent is non-refundable.
- Readiness Deposit — $4,000/MW of the larger of MW energy or MW capacity. Refundable if not selected; otherwise at risk through Phase II per Section 306(A)(5).
- RRI Deposit — an additional $4,000/MW. Fully refundable to non-selected applicants. For selected projects, 50% becomes at-risk at the start of TC2 Phase II, and 100% becomes at-risk on FERC acceptance of the GIA or WMPA. Forfeited if the project withdraws or the GIA/WMPA is terminated. Refunded in full at commercial operation.
For a 250 MW selected RRI project, the RRI Deposit alone is $1 million. Combined with the Readiness Deposit and Study Deposit, the total at-risk financial exposure at FERC acceptance of the GIA can exceed $2.3 million. Site control problems at DP1 are the single most preventable trigger for that exposure to become a forfeiture.
What RRI projects should be doing in the next 60 days
For the 51 selected projects working toward TC2 DP1, three actions matter more than any others in the second quarter of 2026.
- Refresh expired or expiring instruments. Anything with a one-year term keyed to the March 14, 2025 Application Deadline has lapsed below the Section 302 minimum. Execute extensions or replacements that carry a clear term of at least 12 months from the projected DP1 submission date.
- Reconcile entity names across instruments. If site control was assembled in a development LLC and the project has since been assigned to an SPV, a recorded assignment or joinder is required — not just an internal corporate resolution. PJM's review staff verifies the chain on its face, not on representation.
- Update the Site Control Review Spreadsheet. Both the Document Details tab and the Decision Point 1 tab need to be current. The spreadsheet is the document PJM uses to drive its DP1 deficiency review — if the spreadsheet has not been updated, the application is treated as not having been refreshed.
Glossary
- RRI — Reliability Resource Initiative. PJM's one-time acceleration of shovel-ready high-reliability projects, established under FERC Docket ER25-712-000.
- UCAP — Unforced Capacity. The capacity rating used by PJM in the RPM auction and the basis for the RRI weighted scoring criteria.
- ELCC — Effective Load Carrying Capability. A class-based capacity accreditation method used in RRI's market impact scoring (worth up to 20 points).
- TC2 — Transition Cycle #2. The second of two transition cycles bridging the legacy serial queue and the new cycle-based process. RRI projects join TC2 after selection.
- ASA — Application and Studies Agreement. The executed agreement governing the RRI applicant's participation in TC2.
- WMPA — Wholesale Market Participation Agreement. The agreement under which a generation project sells output into PJM markets.
- GIA — Generator Interconnection Agreement. Tariff Part IX, Subpart B form agreement, governing physical interconnection.
- MFO / CIR — Maximum Facility Output / Capacity Interconnection Rights. The two MW values used to size deposits, modeling, and capacity offers. RRI projects are barred from changing either before GIA execution.
- MPT high side — The high-voltage side of the Main Power Transformer. Manual 14H requires 100% site control for the Generating Facility including the MPT high side.
- RPM — Reliability Pricing Model. PJM's capacity market auction. RRI projects are required to offer for 10 consecutive delivery years.
- FRR — Fixed Resource Requirement. The alternative to RPM for capacity commitments, used by load-serving entities that opt out of RPM.
Sources
- PJM IPS Special Session: Reliability Resource Initiative Education, February 2025
- PJM Inside Lines: PJM Chooses 51 Generation Resource Projects, May 2, 2025
- PJM News Release: 51 Generation Resource Projects Selected, May 2, 2025
- Reliability Resource Initiative Results Summary, May 6, 2025 PC
- PJM Manual 14H: New Service Requests Cycle Process — Sections 6 and 7
- Site Control Modification Manual 14H Update, July 23, 2025 MRC